GUIDELINES FOR OBTAINING BUILDING PERMISSION
|
Before the Commencement of Any Construction it is A Must (Mandatory) to obtain
Building Permission under section 433 of Municipal Corporation Act.
The following documents are necessary for applying for Building Permission.
|
Sl .No.
|
Document
|
Copies
|
[01].
|
Building Plans
[Including Site Plan, Key Plan, Detailed Plan]
|
06
|
[02].
|
Section & Elevation [above 300 Sq. Mt. Site Area]
|
12
|
[03].
|
Xerox Copy of Ownership Document
|
01
|
[04].
|
ULC Clearance Certificate [if necessary]
|
01
|
[05].
|
Building Application Form [Prescribed by GMC]
[Cost is Rs. 50/-]
|
01
|
[06].
|
Payment of Fee & Charges
[a] Building License Fee [Code No. 01050102]
[b] Enchroachment Fee [Code No. 01050124]
[c] Betterment Charges [Code No. 01050104]
[d] Development Charges [Payable in Andhra Bank, Hindu College Campus]
[e] Tree Guard Charges [Code No. 01050120]
[f] The Vacant Land Tax @ 1% of property value should be paid
for 1 year, if the site is vacant.
|
|
What is Building License Fee & Material Enchroachment Fee ?
The Building License is levied on the Construction Area and the Material Enchroachment
Fee is Collected for stocking the material on the road [one week only].
|
Why Betterment Charges & Development Charges are collected by GMC ?
Betterment Charges are collected from Unauthorized layouts for providing basic Infrastructure
by the Corporation in those areas.
Development Charges are collected, as per Section 27 of Andhra Pradesh Urban Areas
[Development Act, 1975] to be transferred to Capital Region Development Authority [CRDA] for taking up Major Bye-pass Roads, Fly-overs and parks.
Tree Guard Charges are levied for Raising Plantation in the City. It
is levied at the time of according Building Permission.
|
Regarding Sites exceeding 300 Sq. Mtrs. and 10 Mtrs. Height [Ground + 2 Upper Floors]
in respect of Apartments, Institutional & Commercial Buildings, the following procedure
is to be adopted.
|
Documents Required for Buildings exceeding 10 Mtrs. Height [Ground + 2 Upper Floors]
Vide G.O.Ms.No. 541 M.A., Dated 17-11-2000.
|
[01]. Soil Testing Report.
[02]. Structural Design Drawings.
[03]. Undertaking from the Builder/Firm executing the Construction Work.
[04]. Security Deposit @ Rs. 100/- per Sq. Mtr. of Built up Area.
Note: Please refer G.O.Ms.No. 168 M.A., Dated 07-04-2012.
|
Rules & Regulations :
All Fee & Charges are to be paid in cash in Guntur Municipal Corporation Treasury
or by Demand Draft drawn in any Bank infavour of "The Commissioner, Guntur Municipal Corporation".
|
Fast Track Disposal of Building Approval [Within 24 Hours]
Building Plans will be Approved with in 24 hours subject to payment of 25% extra
fee [excluding betterment charges].
|
|